Tuesday, 21 December 2010

Merry Christmas and a Happy New year.

All The Wates site staff would like to take this opportunity to thank all our neighbours for there continued Patience during the works. If you see anything untowards or damage to the perimeter fencing, Please telephone 01484 454545 and quote Wates site, Rother View Rd, Canklow.
We wish you and your families a very merry xmas and a happy new year.
The site will be closed from the 24th December to the 4th January.

The first Foundations have now been excavated.

The heavy frost has stopped the Bricklayer from constructing the sub-structures.

Friday, 3 December 2010

Snow Stops Play.


Unfortunatley due to the heavy snow and frosts this week (W/E 5th dec 2010),
There has been very little activity on site.
Can I please remind you to ask your children not to play on the site, there could be many hiden dangers under the snow.

Wednesday, 24 November 2010

The installation of a Stone quilt begin.

Now that all the soil nails are grouted and fixed in position, they are covered over with a decorative stone quilt. The quilt is there for aesthetics only.



This is the finished appearance which is very affective and pleasing to the eye.

Soil nailing is now completed.

The placing of six meter long steel rods into the excavated banking is now complete

Wednesday, 3 November 2010

Soil Nailing works commences.

The excavations work has left a 4.5 meter high 60° battered banking to the rear of the proposed dwellings.

The banking is to be retained by driving 5 meter long steel nails into the ground at 1 meter centres.

'X' marks the spot.

Once all the nails are in place they will be covered with a stone wall.

Excavations works completed to Phase 1

The reduced excavations works are now completed to phase 1 of the project.
There has been 487 truck loads removed from site on this phase alone.

Tuesday, 12 October 2010

The Heavy Plant moves in.

The Bulk Excavations works has now commenced, which involves the excavation and removal of 17,500 cubic meters of soil, this equates to in excess of 32,000 tonnes. The work is being carried out by our sub-contractor TKL Earthworks.







Friday, 1 October 2010

Wates are now working in partnership with South Yorkshire Police.

To combat a recent increase of incedents involving damage to the perimeter fencing,

wates are working in partnership with South Yorkshire police.

Regular patrols are now been carried out on evenings and weekends.


PCSO Brian Smith issues Site with unique Smart water.


The Smart Water spray has been placed inside all cabins, which will activate on illegal entry, covering intruders in the water which has a unique DNA to the site.

Thursday, 30 September 2010

The site boundary Hording is now erected.






The site boundary hording has been erected for both site security and to

protect the public from the hazards of a construction site.


Please do not enter the site and ask your children not to play on the site.








Friday, 17 September 2010

Wates Community day.


All the Wates site teams from Canklow and Sheffield Digital Aerials, gave their time for the day to refurbish, clean and paint a local Community footpath and garden area in Sheffield.


Before the team started work.


Look at the transformation!!


Thursday, 9 September 2010

Wednesday, 8 September 2010

The project is in partnership with:


Rotherham Metropolitan Borough Council.



YORbuild.


Synergy Housing Solutions



Work Begins

Wates Living Space are pleased to comence the construction of new residential dwellings,
 Rotherview Rd, Canklow, Rotherham.