Soil Nailing works commences.
The excavations work has left a 4.5 meter high 60° battered banking to the rear of the proposed dwellings.
The banking is to be retained by driving 5 meter long steel nails into the ground at 1 meter centres.
'X' marks the spot.
Once all the nails are in place they will be covered with a stone wall.